Access Certification Tutorial

Last modified 18 Sep 2024 16:08 +02:00

Assuming you’re logged as administrator, you should see the Certification menu items in the main menu:

left menu cert items
Figure 1. Certification definitions table

By default, there are no campaign definitions in the repository. In order to have some definition, you can either import one (e.g. All user assignments) or go through creating certification definition UI (by following Certification → New campaign definition menu item).

After certification definition was added to the system, you can create a campaign based on it. In order to create a campaign, click on the "Create campaign" button (or select menu item) for the appropriate definition. New campaign should be created, successful message should appear. To view the list of campaigns, click on the "Show campaigns" button (or select menu item) or navigate to Certification → Campaigns page through the main menu.

campaigns page
Figure 2. Campaigns page

The campaign is named "All user assignments 1", because there can be - and most probably, will be - more campaigns for a given campaign type. By default, they are named as <campaign definition> plus an increasing number. The campaign has 1 stage, because it was defined as such. It is in the Created state, meaning no action has been done yet.

To start the campaign, click the appropriate "Start campaign" button. The special task is created to process this action, you can follow its progress on the created task details page (the link to it should be displayed on the information message panel). Let’s see the campaign details now by clicking "Details" link on the campaign tile panel.

campaign details
Figure 3. Campaign details view

Left-side summary panel provides basic information about the campaign. We can see that the campaign is now in review stage 1 state. And the stage deadline is in 14 days. There are no decided items yet.

To view certification items which should be reviewed, click on the "Certification → Active campaigns". Active campaigns are shown in the view of tile panels. To view certification items, click "Show items" link.

active campaigns
Figure 4. Active campaigns view

On the certification items page, it is possible to make decision on the certification items with the help of the table menu items.

cert items
Figure 5. Certification items view

By default, the system has 2 available responses. They are:

  1. Accept - the state is accepted as it is.

  2. Revoke - the state is unacceptable, and it should be fixed by removing the particular assignment.

If needded, responses can be extended with the following:

  1. Reduce - the state is unacceptable, but the simple assignment removal is not sufficient. Perhaps it has to be discussed and some solution (e.g. assignment of a less powerful role) has to be found.

  2. Not Decided - the reviewer states he/she is not able or willing to decide.

  3. No Response - the reviewer wants to "undone" his previous decisions regarding this case. (The presence of this button is questionable. Maybe it should be discarded.)

After some decisions are made, it’s possible to view the statistics of the responses and some other data on the campaign details view ("Certification → Campaigns" and click on "All user assignments 1" campaign).

campaign responses panel
Figure 6. Campaign details view - Responses panel

Also, you can view the progress of the reviewers and related tasks on the Statistics panel.

campaign statistics panel
Figure 7. Campaign details view - Responses panel

The stage can be closed either automatically (after defined time, in this case, 14 days), or manually by the owner, at any time. Let’s click on "Close stage" button. Campaign status is changed to "Review stage done". As the number of the defined stages is 1, the campaign is after all available stages. Now there is a possibility to start the remediation, if needed. After "Start remediation" button is clicked, the special task is created to process this action.

remediation started
Figure 8. Starting the remediation

Remediation process removes all assignments marked as "Revoke". After a few seconds, after refreshing the screen, you see that this campaign is over:

closed campaign
Figure 9. Closed campaign

If needed, you can reiterate the campaign by clicking on the "Reiterate campaign" button.